JOINERY PRODUCTION TIMELINE

The following estimated timeframes apply to the production phase of your project

Please note:

  • End-of-year timelines may exceed the estimates below.

  • These are approximate durations, as each project is managed on a case-by-case basis.

  • This is a guide based on our current workload

    Last updated: January 2025

fINAL cONSTRUCTION PLANS

The time required to finalise your detailed Construction Plans for signing. Signing can only proceed once all client selections (e.g., handles) have been made and all necessary information has been provided to Gull Design. The below timeframe is standard, however, this process is client-driven.

1 – 2 Weeks

PRODUCTION

Time from when construction plans are submitted to when the project is ready for installation in our factory.

Laminate (colourboard) Projects: 5-6 Weeks

Two Pack Projects: 6–7 weeks

Shaker Style Projects: 7–8 weeks

Veneer & Solid Timber Projects: Additional time required (TBA)

Timeframes for veneer & solid timber projects depend on material type and availability.

POST-INSTALLATION (OTHER TRADES)

The following times start after a standard or “Dry”(if applicable) Installation is completed.

Stone Benchtops: 5 - 7 working days
Solid Surface Benchtops: 5 – 7 working days

Stainless Steel: 10 – 12 working days
Glass Tops & Splash-backs: 10 – 12 working days


A joinery project consists of two key stages:

  1. Design, quoting, and planning

2. Production

To ensure a seamless process, please review the above timeframes and ensure all necessary details are finalised.

STAGE 1: Design & Quote

Below are the steps to creating a 3D Design and comprehensive Quotation for your project.

Stage 2: Production & Installation

The below Production & Installation Timeline is a guide to approximately how long your project will take to complete.

Many factors contribute to the time taken to produce your high-quality custom joinery, including material delays, 3rd party trade delays and weather.

Larger projects may be split into multiple stages (i.e. Kitchen & Robes in one stage, Laundry & Vanities in another).

Variations may delay your overall project timeline and will only be initiated once they are signed and returned.